The work will be done just north of U.S. 50 in Lawrenceburg.

(Lawrenceburg, Ind.) - Indiana Department of Transportation officials met with contractor representatives this week (JAN 30) at Seymour District offices to discuss operations for overlaying bridge decks on twin Interstate 275 structures located 1.34 miles north of U.S. Highway 50 at Lawrenceburg. Work is scheduled to begin on or after April 1.
Dave O’Mara Contractor, of North Vernon, will hydro-demolish the current driving surface atop 3-span 146-foot-long twin bridges that overpass Action Lane, an access road just north of Belleview Drive, and replace them with 2½-inch-thick concrete deck overlays. This $1,744,288 bridge project includes new concrete bridge rails, approach slabs and guardrail.
Traffic will be restricted to a single lane on both northbound and southbound I-275 bridges. The speed limit will be reduced to 55 mph.
The contract completion date is October 31.
I-275 has a traffic count of 16,110 vehicles per day.

Suspected Measles Case at Laurel Elementary Comes Back Negative
RCCF Announces New Endowment Fund to Provide Support for Adams Township
All Aboard Again: Volunteers Lead Whitewater Valley Railroad’s Recovery
Longtime Law Enforcement Officer, Minister Passes Away
Gov. Braun Announces First Ever Statewide Tip Line for All K-12 Schools
Rising Sun Regional Foundation Awards $133,000 in New Grants




Comments
Add a comment