The work will be done just north of U.S. 50 in Lawrenceburg.

(Lawrenceburg, Ind.) - Indiana Department of Transportation officials met with contractor representatives this week (JAN 30) at Seymour District offices to discuss operations for overlaying bridge decks on twin Interstate 275 structures located 1.34 miles north of U.S. Highway 50 at Lawrenceburg. Work is scheduled to begin on or after April 1.
Dave O’Mara Contractor, of North Vernon, will hydro-demolish the current driving surface atop 3-span 146-foot-long twin bridges that overpass Action Lane, an access road just north of Belleview Drive, and replace them with 2½-inch-thick concrete deck overlays. This $1,744,288 bridge project includes new concrete bridge rails, approach slabs and guardrail.
Traffic will be restricted to a single lane on both northbound and southbound I-275 bridges. The speed limit will be reduced to 55 mph.
The contract completion date is October 31.
I-275 has a traffic count of 16,110 vehicles per day.

Hoosier Hills Credit Union Named Top Credit Union in Indiana for Fourth Year in a Row
South Dearborn Names New Middle School Principal
NWS: Severe Weather Possible Overnight
Human Remains Found in Franklin Co. Identified
Street Closures Announced for Tastes of Summer
One in Custody After Shooting Incident in Cleves




Comments
Add a comment