I-275 Bridge Deck Overlay To Start In April

Monday, February 4, 2019 at 11:49 AM

By Indiana Department of Transportation, news release

The work will be done just north of U.S. 50 in Lawrenceburg.

(Lawrenceburg, Ind.) - Indiana Department of Transportation officials met with contractor representatives this week (JAN 30) at Seymour District offices to discuss operations for overlaying bridge decks on twin Interstate 275 structures located 1.34 miles north of U.S. Highway 50 at Lawrenceburg. Work is scheduled to begin on or after April 1.

Dave O’Mara Contractor, of North Vernon, will hydro-demolish the current driving surface atop 3-span 146-foot-long twin bridges that overpass Action Lane, an access road just north of Belleview Drive, and replace them with 2½-inch-thick concrete deck overlays. This $1,744,288 bridge project includes new concrete bridge rails, approach slabs and guardrail.

Traffic will be restricted to a single lane on both northbound and southbound I-275 bridges. The speed limit will be reduced to 55 mph. 

The contract completion date is October 31.

I-275 has a traffic count of 16,110 vehicles per day.

 

More from Local News


Events

York Ridge Road Closure Announced

The closure will begin in early May.

Closure Planned on State Road 250 in Switzerland Co.

S.R. 250 to reopen west of Township Line Road, to close east of Fairview Road.

Indiana Unemployment Rate Falls, Local Rates Rise in Latest Report

The report for February 2026 was released this week.

EC's Perkins Sets School Record in 200 Meter Dash

The IU commit was on fire on Wednesday night.

Switz. Co. 7th Grader Sets School Record in Shot Put

The record was set at Wednesday night's quad meet in Vevay.

Local Sports Report - April 22, 2026

Report missing stats and scores to news@eaglecountryonline.com

On Air

George Strait I Just Want To Dance With You 1:46
Brett Eldredge Wanna Be That Song 1:42
Jason Aldean Big Green Tractor 1:38
Tucker Wetmore Wind Up Missin' You 1:35