I-275 Bridge Deck Overlay To Start In April

Monday, February 4, 2019 at 11:49 AM

By Indiana Department of Transportation, news release

The work will be done just north of U.S. 50 in Lawrenceburg.

(Lawrenceburg, Ind.) - Indiana Department of Transportation officials met with contractor representatives this week (JAN 30) at Seymour District offices to discuss operations for overlaying bridge decks on twin Interstate 275 structures located 1.34 miles north of U.S. Highway 50 at Lawrenceburg. Work is scheduled to begin on or after April 1.

Dave O’Mara Contractor, of North Vernon, will hydro-demolish the current driving surface atop 3-span 146-foot-long twin bridges that overpass Action Lane, an access road just north of Belleview Drive, and replace them with 2½-inch-thick concrete deck overlays. This $1,744,288 bridge project includes new concrete bridge rails, approach slabs and guardrail.

Traffic will be restricted to a single lane on both northbound and southbound I-275 bridges. The speed limit will be reduced to 55 mph. 

The contract completion date is October 31.

I-275 has a traffic count of 16,110 vehicles per day.

 

Events

Prepping Future Chefs at Science Behind Cooking Camp

Genesis: Pathways to Success held the camp at South Ripley High School.

KYTC: Celebrate This Fourth of July Weekend Responsibly

High-visibility patrols and sobriety checkpoints throughout the holiday period.

Versailles Native Wins Lions Pride 5K

The next Southeastern Indiana Racing Circuit event is July 12 in St. Leon.

IHSBCA Announces 2025 Academic All-State Team

Players from Batesville, East Central and Madison earned the honor.

On Air

Your Hometown Radio Station playing
John Conlee - Rose-Colored Glasses

Corey Kent This Heart 1:52
Michael Ray Spirits & Demons 1:47
Holly Dunn You Really Had Me Going 1:45
Pat Green Wave On Wave 1:41