INDOT: US 52 Slip Repair Project Will Go Into September

Friday, May 31, 2019 at 10:23 AM

By Indiana Department of Transportation, news release

The project is slated to begin Monday in Franklin County.

(Franklin County, Ind.) - U.S. 52 will close on or after Monday, June 3, weather permitting, between New Trenton and Cedar Grove for emergency slide correction work.

INDOT contractor GeoStabilization International will place a soil nail wall on the east side of the roadway, approximately one mile north of New Trenton. Soil boring will also take place on the west side of the road, along the railroad and Whitewater River.

U.S. 52 will be closed for 90 days and will reopen as one lane with a temporary traffic signal in September. The repair is expected to be complete by late December and the road will open as two lanes at that time.

The official state detour for the closure is S.R. 46 to S.R. 1 to the intersection of U.S. 52/S.R. 1, north of Cedar Grove.

More from Local News


Events

Groundbreaking Held at Short Street Pavilion Site

The open-air structure is planned to be completed later this year.

North Vernon Man Facing Drug Charges in Dearborn Co. After Traffic Stop

Police allegedly seized 29 grams of fentanyl.

USPS to Host Job Fairs in Osgood, Versailles

Open positions pay up to $20.38 per hour.

Bill Brinkman to Receive Outstanding Official Award

Brinkman is in his 35th year as an official.

Seven Earn Academic All-State Honors from ICGSA

To be eligible, student-athletes have to have a GPA of 3.5 or higher.

Craig, Henry Named to HBCA East All-Star Team

Two Ohio River Valley Conference stars will team at the HBCA East/West All-Star Classic. 

On Air

Your Hometown Radio Station playing
Zach Top - I Never Lie

Joe Diffie It's Always Somethin' 2:27
Trisha Yearwood There Goes My Baby 2:23
Mark Chesnutt Gonna Get A Life 2:20
Cole Swindell Drinkaby 2:17