Parkside Construction Hits A Soft Spot

An underground surprise is going to tack a few days onto the reconstruction of Parkside Avenue in Greendale.

Parkside Avenue construction. File photo.

(Greendale, Ind.) - It will take a little longer than first expected to complete the repaving project on Parkside Avenue in Greendale.

City manager Steve Lampert explained Monday that crews discovered about a 600 foot area of soft soil in the area of Heck Street.

“It appears to be an area on top of 24-inch storm pipe that was installed in 1950s and covered with sand,” said Lampert.

Contractor crews will have to dig out that soft soil and replace it with stone.  So, paving that was supposed to take place Tuesday, August 13 won’t be able to happen until Thursday, August 15, weather permitting.

Until then, Heck and Hillside will be shut down at Parkside Avenue. The final layer of asphalt will be poured in coming weeks, Lampert said last week.

Parkside Avenue has been under reconstruction since April.

RELATED STORIES:

Parkside Avenue Reconstruction Project Nearing Finish Line

Parkside Avenue Reconstruction Project Begins April 26

More from Local News


Events

UPDATE: Pavement Rehabilitation Work Continues on U.S. 50 in Aurora

Phase 1B is in effect as crews have completed additional items ahead of schedule.

KYTC Gives Update, Answers FAQs Regarding Carroll Cropper Bridge Project

The overall project will go into the summer months.

Main Street Brookvillle Selected to Partner with IU on Creative Placemaking Initiative

The initiative will see two murals installed in Brookville.

Seven Earn ORVC Weekly Honors

ORVC Report for April 14-19.

Local Sports Report - April 23, 2025

Report missing stats and scores to news@eaglecountryonline.com

On Air

Your Hometown Radio Station playing
Hank Williams Jr. - Whiskey Bent And Hell Bound

Brad Paisley Then 21:25
LoCash One Big Country Song 21:21
Ronnie Milsap Any Day Now 21:17
Shenandoah If Bubba Can Dance 21:13